ABC: Multiskilled Crews Can Cut Construction Completion Time by 30%

Research highlighted by ABC found multiskilled crews can finish closely sequenced work about 30% faster by cutting handoffs between trades.

Multiskilled construction crews can reduce completion time by about 30% and increase production by 37% to 50% where multiple trades must work in tight sequence, according to research Associated Builders and Contractors (ABC) highlighted September 30.

The findings come from the Simplar Foundation’s second multiskilling report, based on field trials of 11 construction activities with 10 trade handoffs at the Cianbro Institute in Pittsfield, Maine.

“These findings show that multiskilling is more than a workforce strategy. It can also be a project-delivery strategy,” said Tiffany Robinson, ABC vice president of workforce and safety policy. “Careers in Construction Month is an opportunity to underscore the value of building broader skills that bolster productivity on jobsites. Multiskilling can expand workers’ capabilities and career opportunities while giving the industry a practical strategy to address persistent labor shortages and increase America’s capacity to build.”

Workers did not have to finish individual tasks faster. The gains came from fewer handoffs between crews.

In one comparison, two multiskilled workers completed a scope spanning seven trade functions, while the single trade workflow used 12 workers and handed off the work 10 times. Both crews held credentials for each trade performed.