ABC: Final Multiskilling Study Finds Construction Schedules Up to 38% Shorter

The last report in a national research series found that multiskilled crews finished work in 22% to 38% fewer workdays than a single trade approach.

Associated Builders and Contractors (ABC) on November 12 highlighted the Simplar Foundation’s third and final multiskilling report, which found schedules can shrink by as much as 38%.

Researchers reviewed nearly 90,000 labor hours on 18 projects involving 11 contractors. Restricting workers to one trade would have required 28% to 62% more workdays for the same work.

On 73% of project days, single trade staffing would have left at least one trade short of labor, and the busiest days needed over one third more workers. Crew members performed an average of 3.2 trades or skills, with 80 unique combinations across 18 trades.

“America faces a fundamental challenge: We have more to build than our workforce can currently support,” said ABC President and CEO Michael Bellaman. “This research demonstrates that a solution is already within reach. By investing in our craft professionals, expanding their skills and removing unnecessary barriers to using those skills, we can create more opportunity for workers and greater capacity for contractors to build America.”

ABC is calling for policies that recognize proven worker skills, expand training and let qualified workers safely work across several trades.